HOMEOWNER GUIDANCE

Deck Permit in Redmond, WA: What Homeowners Need to Know

Planning a deck in Redmond? See when the City of Redmond requires a permit, what the application includes, how inspections work and how to avoid delays.

Redmond homeowner checks plans beside a deck

If you are building or replacing a deck in Redmond, you almost certainly need a building permit. Redmond’s building permit FAQ says a permit is required for decks attached to a structure, decks over 200 square feet, and decks more than 30 inches above grade. Only small, low, detached decks are exempt. As a Redmond deck builder based in Everett, we build with composite, PVC and cedar, use our own in-house crews, and back our installations with a warranty. This guide explains how the permit works so your project does not stall at the counter.

Cactusdecking
Plan a Deck That Fits Your Home
Cactus Decking builds custom decks in composite, PVC, or cedar, with in-house crews and warranty-backed installations.
Visit

TL;DR

  • A Redmond deck needs a building permit if it is attached to the house, over 200 sq ft, or more than 30 inches above grade.
  • The exemption is narrow: detached, 200 sq ft or less, 30 inches or lower, not over a basement or story below, and not serving a required exit door.
  • The application needs a site plan and drawings of footings, framing, guards and stairs. Redmond publishes its fees in a yearly schedule, so confirm the current figures with the city.
  • Inspections are requested during construction, before any work is covered, and a final inspection closes the permit.
  • Confirm current rules with the City of Redmond before you start. We offer free on-site estimates at (425) 322-6981.

Table of Contents

When a Redmond deck needs a permit

The City of Redmond’s Fences & Decks page states that decks need a building permit under the International Residential Code (IRC), the model building code Washington adopts with state amendments. In practice, most decks homeowners build here trigger one, because most are attached to the house.

You need a permit if the deck:

  • is attached to a dwelling,
  • is larger than 200 square feet, or
  • is more than 30 inches above the ground at any point.

That is the rule in the city’s building permit FAQ. Replacing a deck counts as construction or alteration, so a tear-down and rebuild is not a way around it. If you are unsure whether a repair or resurfacing job crosses the line, ask the city before you begin.

What is exempt

Redmond’s Work Exempt from Permit handout lists the conditions for a deck to skip the permit. All of them must be true:

  • 200 square feet or less
  • no more than 30 inches above grade at any point
  • not attached to a dwelling
  • not serving the exit door required by IRC Section R311.4
  • not over a basement or story below

The city’s Residential Permits page repeats the 30-inch and basement conditions for detached decks. A low freestanding platform in the corner of a yard may qualify. A deck off your back door will not.

Exempt from a permit does not mean exempt from the rules. Your deck still has to respect zoning, setbacks and any HOA covenants, so check the Redmond Zoning Code tools the city points to on its Residential Permits page.

What the permit application includes

Redmond publishes a Residential Deck Application Packet (for applications submitted on or after May 1, 2025). It asks for:

  1. An application form.
  2. A site plan with the planning tables completed.
  3. Plans showing the deck footprint, structural and attachment details, a footing plan, elevations, guardrails and stairs, and framing details.

Structural calculations are not required for prescriptive IRC designs, which follow the code’s standard tables. If calculations are required, they must be stamped and signed by a Washington State design professional. A Flood Elevation Certificate is required in the 100-year floodplain, and the city may ask for a geotechnical report on certain sites. Contractors working in the city need a City of Redmond business license.

The packet also sets the design conditions your plans must use, including a 110 mph design wind speed, a 15 psf ground snow load, a 12-inch frost line depth and a 1,500 psf soil bearing capacity unless a geotechnical report says otherwise. The Applications & Forms page also notes that updated design standards took effect June 18, 2025 for projects covered by them.

The city may route your permit through Fire, Land Use and Civil Engineering review depending on scope, so a simple-looking deck on a sloped or constrained lot can take longer than expected.

Permit fees

Redmond sets fees by project valuation. Its residential fee schedule effective February 1, 2026 builds the permit fee from a tiered valuation table, adds plan review at 65% of the building permit fee, a 4% technology surcharge on total fees and a State Building Code fee per unit. It also lists separate charges such as deck planning review and hourly rates for additional plan review.

Fee schedules are updated, so use the live schedule and the city’s permit staff to price your specific deck. We do not quote permit fees here, and the number depends on your project’s valuation.

Permit fees

Code requirements your plans must meet

The permit is where the city checks that the deck is safe. Washington’s 2021 IRC with state amendments, effective March 15, 2024, sets these basics:

  • Guards (railings): required on open-sided walking surfaces more than 30 inches above the floor or grade below, at least 36 inches high. Guards along stairs may be 34 inches minimum.
  • Posts: sized by post height and the area of deck each one carries, per Table R507.4. A 4x4 post, for example, is limited to small areas at tall heights, which is why larger decks use 6x6 posts.

The Washington residential final inspection checklist adds what inspectors look for:

  • the deck is positively attached and supports lateral and live loads, with a 40 psf live load minimum,
  • treated or naturally decay-resistant lumber, with cut surfaces treated,
  • hot-dipped galvanized, stainless, silicon bronze or copper fasteners for treated wood,
  • ledger attachment per IRC Table R507.2.3,
  • hold-down tension devices on decks 30 inches or more above grade,
  • footing bottoms at least 12 inches below grade.

These details are why railings and stairs deserve planning at the design stage. See our work on deck railing systems and deck stairs in Redmond.

Inspections: what happens after approval

Per the city’s Residential Permits page, inspections are requested throughout construction and before any work is covered up. They are scheduled through the city’s online system or by phone at 425-556-2435, using the IVR pin on your permit record. Keep the permit card and approved plans on site at all times. A final inspection is required, and any trade permits must be approved before the building permit final.

If you have questions about the process, the city’s permit line is 425-556-2900. The Redmond Building Division is at 15670 NE 85th St.

What is specific to Redmond

Three local factors shape a deck project here.

The City of Redmond permit center. Permits go through the city, not the county. Confirm current forms, fees and review times with the city before you commit to a schedule.

HOAs in newer subdivisions. Many Redmond neighborhoods are newer subdivisions with homeowners associations. An HOA may require its own approval of size, color, materials and railing style. City approval and HOA approval are separate, so get both before you order materials.

What is specific to Redmond

Wet winters. Redmond’s long rainy season, moss and freeze-thaw cycles are hard on wood and fasteners. That is one reason the code calls for decay-resistant lumber and corrosion-resistant hardware, and why we build with composite, PVC and cedar, materials suited to Northwest weather. Our deck design service in Redmond plans for drainage, airflow and material choice from the start. For rot, ledger or railing problems on an existing deck, see deck repair in Redmond.

A practical sequence for Redmond homeowners

  1. Decide the scope. Size, height, attachment and whether you are replacing or adding all affect permit needs.
  2. Check HOA rules. Get written approval if your community requires it.
  3. Prepare the drawings. A site plan and construction plans matching the city’s packet.
  4. Submit to the City of Redmond and respond to review comments.
  5. Build to the approved plans, and request inspections before anything is covered.
  6. Pass final inspection and keep your records.

If you want a second set of eyes before you submit, a similar walk-through for neighboring Seattle is in our Seattle deck permit guide, though Redmond’s rules and forms are its own.

Our approach to Redmond permits

Most permit delays come from plans that do not match what will actually be built. A deck that is drawn, permitted and built by people who talk to each other avoids that.

That is why we run in-house build crews rather than subcontractors, and why we walk you through a clear process from consultation to construction. Our installations are warranty-backed, and we build with composite, PVC and cedar so you can choose the look and upkeep that fit your yard and your rainy seasons.

For permits, always confirm current requirements with the City of Redmond permit office. We will work through the scope with you at the estimate.

Vlad

Plan your Redmond deck with Cactus Decking

We design, build and replace residential decks, including railings, stairs, covers and lighting, from our base in Everett. For a new deck, see deck installation in Redmond; for a tear-out and rebuild, see our deck replacement service.

Cactusdecking

We offer free on-site estimates for Redmond homeowners.

FAQ

Do I need a permit to replace my deck in Redmond?

Yes, in most cases. Replacement is construction or alteration, and any deck attached to the house, over 200 square feet or more than 30 inches high needs a building permit under the city’s rules. Confirm your specific case with the City of Redmond.

Can I build a small deck without a permit?

Only if it is detached, 200 square feet or less, no more than 30 inches above grade, not over a basement or story below, and not serving a required exit door. Zoning and HOA rules still apply.

How tall can a deck be without a railing?

Washington’s 2021 IRC requires guards where the walking surface is more than 30 inches above the floor or grade below, and the guard must be at least 36 inches high. Stair guards can be 34 inches minimum.

Does Redmond inspect decks?

Yes. Inspections are requested during construction and before work is covered, and a final inspection is required to close the permit.

Get a free on-site estimate

Ready to plan your Redmond deck? Call us at (425) 322-6981 or request your free on-site estimate.

Sources

Vlad, Estimate & Design at Cactus Decking
WRITTEN BY

Vlad, Estimate & Design at Cactus Decking

Vlad prepares Cactus Decking's written estimates and helps Everett-area homeowners compare layouts, materials, railings, stairs, covers, and lighting before a deck is built.

Meet the Cactus Decking team
LOCAL HELP

Ready to build a deck that lasts?

Cactus Decking is a deck builder in Everett, WA. We can look at your deck, explain the options, and give you a free written estimate.

Rain-season tip: Design, drawings, and any permit review can be finished in the rain season, so building can start when the yard dries out.